Controls integration requires documentation of what was installed.
What You Might Be Looking At
packet of documentation showing what controls devices were installed, where, and how wired
Apprentice words: controls paperwork, BAS docs, commissioning docs, handoff papers
Trade terms: BAS handoff, controls documentation, commissioning documentation, as-built controls
Check First
What Not To Do
Don't install controls without documenting. Don't assume controls contractor knows what you installed. Don't remove labels or tags.
What can go wrong: Commissioning delay, controls can't be programmed, warranty issues, owner rejection, re-work to trace wiring
Better Foreman Question
For the BAS handoff, what documentation does controls contractor need? Should I label wires and device locations as I install?
Verify With
Reference type: project specs, controls submittals
Source to verify: Project commissioning plan, controls spec 25 10 00
Safe wording: BAS handoff requirements vary by project and controls contractor. Verify against project commissioning plan.