Controls integration requires documentation of what was installed.

Green / Field Check3rd yearBatch 2

What You Might Be Looking At

packet of documentation showing what controls devices were installed, where, and how wired

Apprentice words: controls paperwork, BAS docs, commissioning docs, handoff papers

Trade terms: BAS handoff, controls documentation, commissioning documentation, as-built controls

Check First

Is there a controls device schedule?
Are device locations marked on as-builts?
Is wiring labeled at both ends?

What Not To Do

Don't install controls without documenting. Don't assume controls contractor knows what you installed. Don't remove labels or tags.

What can go wrong: Commissioning delay, controls can't be programmed, warranty issues, owner rejection, re-work to trace wiring

Better Foreman Question

For the BAS handoff, what documentation does controls contractor need? Should I label wires and device locations as I install?

Open In Ask Foreman

Verify With

Reference type: project specs, controls submittals

Source to verify: Project commissioning plan, controls spec 25 10 00

Safe wording: BAS handoff requirements vary by project and controls contractor. Verify against project commissioning plan.