How do I ensure all VAV damper blades are in the open position before system blow-down

4th YearDampers, Fire/Smoke & Life SafetyStop / Verify

Coordinate with the temperature controls technician to command all digital VAV box actuator motors to drive into their 100% full open position overrides via their central software control board. * If the controls aren't powered on yet, you must manually decouple the actuator shaft set-screws and rotate the damper blades by hand to full open before starting the primary fans.

Ask a jobsite questionBack to Dampers, Fire/Smoke & Life Safety

Plain-English answer

Coordinate with the temperature controls technician to command all digital VAV box actuator motors to drive into their 100% full open position overrides via their central software control board. * If the controls aren't powered on yet, you must manually decouple the actuator shaft set-screws and rotate the damper blades by hand to full open before starting the primary fans.

Field checklist

Ask Foreman

Hey boss, I’m on tab / startup prep and need verification before I touch this: How do I ensure all VAV damper blades are in the open position before system blow-down? Do you want me to stop here and check the approved detail, submittal, or inspector/manufacturer requirement first?

Verify before acting

Use this as training guidance. The foreman, approved drawings, project specs, manufacturer installation instructions, employer safety policy, and AHJ/code requirements always control the final answer.