TinnerFlow logoTinnerFlow™
Mistake & recovery · #167

Not accounting for diversity factor when sizing a multi-zone VAV supply duct main

4th YearDuct Systems

In a VAV system, not all zones reach peak load simultaneously. Apply an appropriate diversity factor to the supply main to avoid oversizing the duct and t…

Search Field RescueAsk ForemanOpen in mistake guide

Safer field move

In a VAV system, not all zones reach peak load simultaneously. Apply an appropriate diversity factor to the supply main to avoid oversizing the duct and the fan. Consult the mechanical engineer for the design diversity assumption.

Ask Foreman

Can you verify this before I keep going? I’m looking at: Not accounting for diversity factor when sizing a multi-zone VAV supply duct main. What’s the approved correction for this job?

Do not

Do not hide, force, cover, or “make it work” if this affects safety, access, airflow, rated assemblies, supports, equipment, or inspection. Stop and verify the approved correction.

Related mistakes