Before You Reroute

Printable field checklist for before you reroute.

First move

Stop and document why the planned route does not work before changing anything.

Check before moving

  • Latest drawing/revision
  • Conflict trade and exact location
  • Size/elevation/clearance
  • Airflow/TAB impact
  • Support/seismic changes
  • Equipment and damper access

Photo ID to collect

  • Wide conflict photo
  • Close obstruction photo
  • Measurement/elevation photo
  • Print markup photo

Ask this

“The planned route hits this obstruction. Do you want me to hold this section until we get direction?”

Do not

Do not reroute duct just to make today’s piece fit.