Verify Roof Curb and RTU Match Before the Lift

Equipment Connections: RTU, AHU, VAV, Fans & LouversSTOP / VERIFYField judgment

Core Answer

Confirm the curb, adapter, unit model, opening arrangement, rail orientation, and supply/return locations before crane day.

Open in Field RescueOpen Category

What to Check First

Ask Foreman

Before crane day, can we verify this curb and adapter against the actual RTU model, opening orientation, and approved submittal?

Text to Foreman

Do Not Do This

Do not rely only on a shipping label or assume similar unit sizes use the same curb openings.

Why This Matters

A mismatch discovered during the pick can stop the crane, expose the roof, or lead to unsafe field modifications.

Verify against: equipment and curb submittals, approved shop drawings, lift plan, foreman/PM verification.