Document Seismic Bracing Before It Is Covered

Seismic Bracing, Sway Control & Structural CoordinationSTOP / VERIFYField judgment

Core Answer

Capture brace location, direction, angle, attachment, hardware, labels, and surrounding clearance while the complete installation is still visible.

Open in Field RescueOpen Category

What to Check First

Ask Foreman

Which seismic brace locations and attachment details need photos or inspection signoff before this ceiling or shaft closes?

Text to Foreman

Do Not Do This

Do not take one distant photo, hide unapproved changes, or cover attachments before required inspection.

Why This Matters

Seismic acceptance often depends on proving the installed assembly matches the approved engineered package.

Verify against: approved seismic package, inspection plan, project QA/QC procedure, engineer/AHJ/foreman direction.