Condensate Coordination at HVAC Equipment

Coordination, Clashes, Sequencing & ReworkVERIFYField judgment

Core Answer

Protect the drain connection, required slope, trap, cleanout, insulation, and service access while routing duct and supports around equipment.

Open in Field RescueOpen Category

What to Check First

Ask Foreman

The condensate route needs [direction/slope]. Can we lock the drain and service space before I finalize this duct and support layout?

Text to Foreman

Do Not Do This

Do not crowd the drain connection, block trap removal, or force gravity piping to dodge a duct route after the equipment is set.

Why This Matters

Condensate problems create leaks, shutdowns, ceiling damage, and commissioning failures.

Verify against: equipment manufacturer instructions, plumbing/mechanical drawings, coordination set, foreman direction.