Content Gap Batch 8Two Trades Need the Same Space
Coordination, Clashes, Sequencing & Rework⚠️ VERIFYField workflow
Core Answer
Stop the affected work, document the exact clash, and compare both trades against the current coordinated set before anyone reroutes in the field.
Open in Field RescueOpen Category
What to Check First
- Mark room, grid, elevation, and clash dimensions
- Photograph both systems and nearby constraints
- Verify drawing revision and installation status
- Identify fixed constraints such as slope, clearance, access, and rated assemblies
- Bring one or more workable options to the foreman without moving another trade’s work
Ask Foreman
Duct and [trade] occupy the same space at [grid/elevation]. The coordinated set shows [condition]. Do we hold, reroute, or send an RFI?
Text to Foreman
Do Not Do This
Do not move, cut, disconnect, or build around another trade’s work without coordination and approval.
Why This Matters
An undocumented workaround often creates the next conflict a few feet away.
Verify against: coordination set, current discipline drawings, RFI process, foreman/VDC direction.