Roofing Coordination Before a Duct or Curb Penetration

Coordination, Clashes, Sequencing & Rework⚠️ STOP / VERIFYField workflow

Core Answer

Coordinate the opening, curb, flashing, membrane protection, temporary weather seal, and roofing warranty requirements before cutting or setting work on the roof.

Open in Field RescueOpen Category

What to Check First

Ask Foreman

Before we cut or set this curb, has roofing approved the detail, opening, temporary dry-in, and final flashing sequence?

Text to Foreman

Do Not Do This

Do not cut the roof or apply random sealant/flashing materials without roofing and project approval.

Why This Matters

A technically correct duct opening can still create a roof leak or void the roof warranty.

Verify against: roofing details/spec, curb/equipment submittal, structural opening approval, roofer/foreman direction.