Vibration Isolation at Fans and Air-Handling Equipment

Equipment Connections: RTU, AHU, VAV, Fans & LouversVERIFYField judgment

Core Answer

Keep the equipment isolated from rigid duct, piping, conduit, and supports exactly as the approved detail shows.

Open in Field RescueOpen Category

What to Check First

Ask Foreman

Can we verify the isolator setup and every possible vibration bridge before this fan or air handler is started?

Text to Foreman

Do Not Do This

Do not hard-connect the duct, bottom out springs, remove shipping restraints early, or add supports that bypass the isolators.

Why This Matters

One rigid bridge can transmit vibration and noise through the structure even when the equipment has proper isolators.

Verify against: equipment and isolator submittals, vibration-control detail, manufacturer startup instructions.