Field problem

Verify first

Verify before you commit. Cheap to catch now.

The shop sent the wrong fitting or elbow and the duct run is stopped

Do not field-modify the wrong fitting first. Stop the run, document the mismatch, measure what is needed, and bring the foreman a clear replace/adjust decision.

Joints, TDC, Flanges & Connections 2nd Year YELLOW

Watch out

Check

Steps

Say this to your foreman

The fitting staged for [location] is a [what it is], but the drawing/detail shows [what is needed]. I measured [size/angle/connection]. Do you want a replacement, field modification, or a different route?