Before RTU sets on curb - what do I check?
Before the pick, verify curb tag, orientation, gasket path, supply/return openings, access clearances, and loose debris. This is the last cheap moment to catch a rotated or wrong curb/unit setup.
Stop if Before this RTU gets picked, can we verify tag, orientation, gasket path, openings, and service access so we do not land it wrong?
Watch out Do not let the unit land just because the crane is waiting if the curb, openings, gasket, or orientation is wrong.
Check Match unit tag to curb tag, plan location, and orientation. Verify supply/return openings line up and nothing is blocking the duct path. Check gasket path, curb top, corners, loose screws, debris, and bent metal. Look at service access, coil pull, filters, gas/electrical/control routes, and roof hatch path. Call out mismatch before the crane picks or before the unit lands.
Steps Match unit tag to curb tag, plan location, and orientation. Verify supply/return openings line up and nothing is blocking the duct path. Check gasket path, curb top, corners, loose screws, debris, and bent metal. Look at service access, coil pull, filters, gas/electrical/control routes, and roof hatch path. Call out mismatch before the crane picks or before the unit lands.
Say this to your foreman Before this RTU gets picked, can we verify tag, orientation, gasket path, openings, and service access so we do not land it wrong?