What do I do if the structural beams shown on the print don't exist in the field?
3rd YearSealing & InsulationRED · Stop / Verify
Stop installation immediately along that line segment.
TinnerFlow™3rd YearSealing & InsulationRED · Stop / Verify
Stop installation immediately along that line segment.
Stop installation immediately along that line segment.
Take accurate photos and field measurements showing the real structural elements that are currently in the way. Bring this information to the foreman so they can submit an official RFI (Request for Information) to the structural engineer for an alternate approved hanger attachment design. Never drill or anchor randomly into alternative structural elements without approval.
Use this as training guidance. The foreman, approved drawings, project specs, manufacturer installation instructions, employer safety policy, and AHJ/code requirements always control the final answer.