Not documenting verbal owner requests in writing before performing extra work

4th YearCoordination & Professionalism

Before performing any work requested verbally by the owner or GC outside the contract scope, send a confirming email or written notice. Never perform extr…

Search Field RescueAsk ForemanOpen in mistake guide

Safer field move

Before performing any work requested verbally by the owner or GC outside the contract scope, send a confirming email or written notice. Never perform extra work without written authorization — verbal agreements do not protect you in a dispute.

Ask Foreman

Can you verify this before I keep going? I’m looking at: Not documenting verbal owner requests in writing before performing extra work. What’s the approved correction for this job?

Do not

Do not hide, force, cover, or “make it work” if this affects safety, access, airflow, rated assemblies, supports, equipment, or inspection. Stop and verify the approved correction.