What do I do when installing from old coordination drawing?
Coordination, Clashes, Sequencing & ReworkCoordination starter — document before changing work
If you already installed from an old revision, stop installing more, mark what was installed, and get the current drawing before anyone changes or removes work.
Get the latest drawing/revision or ask who has it.
Mark/photo exactly what was installed from the old print.
Compare installed work to current route.
Ask whether to hold, correct, or document for RFI/rework.
Ask foreman
I installed this from an older revision. Here is what is installed and where. Do you want me to hold here while we compare to the current drawing?
Do not
Do not keep installing from the old print or start ripping out work without direction.
Why it matters
Old revisions create blame and rework; documenting the installed scope protects the crew and helps the foreman decide the next move.
Search words: coordination clashes rework revision coordination old coordination drawing revision current sheet install old coordination drawing revision current sheet install coordination rework What do I do when installing from old coordination drawing? If you already installed from an old revision, stop installing more, mark what was installed, and get the current drawing before anyone changes or removes work. coordination clashes rework revision coordination old coordination drawing revision current sheet install