What do I do when a rigid seismic brace is pressing against another trade line?

Seismic Bracing, Sway Control & Structural Coordination⛔ STOP / GET DIRECTIONField answer expansion

📖 Verified core answer

A rigid brace should not pin or rub another trade line. Stop, clear the conflict, and revise the brace angle/attachment by approved direction.

Open in Field RescueOpen category

Field verification checklist

Ask foreman

Our rigid seismic brace at [location] is hard against [other trade line]. I stopped tightening it. Do you want the brace angle/anchor revised and the other trade notified?

Text to foreman

Route options

AMake the field correction only if it is within your assignment and the approved method.
BHold and document the condition if the fix affects support load path, structural steel, seismic restraint, life safety, another trade, or inspection.
CBring the foreman/detailer the location, what you checked, and what decision you need before loading, cover, startup, or rework.

Do not do this

Do not let a seismic brace use another trade pipe, conduit, or cable tray as a bumper.

Why this matters

A brace that rubs another system can damage critical utilities and fail seismic/coordination inspection.