Check orientation, access, inlet/outlet size, controller/actuator side, hanger support, damper access, and whether the duct connection will block service or TAB.
Keep actuator, reheat coil, controls, and service panels reachable
Support duct so the box is not carrying the run
Ask foreman
Before I tie into this VAV, can you verify the orientation and access side? I want to make sure the controller, damper, and service panel stay reachable.
Do not
Do not bury the controller, coil, damper, or access side behind duct, flex, insulation, or hangers.