CONTENT GAP BATCH 12 · Receiving, Staging & Shop-to-Field Flow
Reject or Repair? Hold Damaged Duct Until the Decision Is Clear
VERIFYFast answer
Quarantine a damaged or questionable piece so it is not installed while the repair-versus-remake decision is still open.
What to check
- Tag or separate the piece from approved material.
- Record the piece mark, location, damage, dimensions, and schedule impact.
- Identify whether the issue affects fit, pressure boundary, reinforcement, coating, liner, appearance, listing, or equipment connection.
- Route the decision through the foreman and the required shop, manufacturer, project, or engineering authority.
Do not
Do not install a questionable piece because the crew needs production or because replacing it may take time.
Ask the foreman
“This piece is isolated and documented. The damage affects the flange and liner; who is making the repair-versus-remake call before we install around it?”
Why it matters
Once surrounding duct is installed, a simple delivery problem can become a major removal problem.