Apprentice question
Verify first
Verify before you commit. Cheap to catch now.
Gravity Plumbing (Sewer/Waste Mains) & Roof Drains: Absolute first priority. They must slope continuously at a precise angle to function and cannot easily rise or fall over obstacles.
['Gravity Plumbing (Sewer/Waste Mains) & Roof Drains: Absolute first priority. They must slope continuously at a precise angle to function and cannot easily rise or fall over obstacles.', 'Large Sheet Metal Ductwork: Second priority. It is bulky and requires massive paths, but can accommodate planned offsets, drops, and transitions around structural obstacles.', 'Pressurized Fire Sprinkler Lines & Electrical Conduits: Lowest layout priority. They can easily loop, bend, and drop over or under other major system runs without affecting performance.']
who has the right-of-way in a ceiling plenum: ductwork, gravity plumbing, or sprinklers?