Field problem

Verify first

Verify before you commit. Cheap to catch now.

What should I check before fastening duct to an equipment cabinet?

Confirm the manufacturer/project detail before fastening to equipment. Watch for cabinet penetration depth, internal coils, wiring, controls, drain pans, access panels, and service clearances.

Support duct independently before tightening the equipment connection. Equipment cabinets, VAV boxes, fans, louvers, and flex connectors are connection points, not hangers.

Equipment Connections: RTU, AHU, VAV, Fans & Louvers 2nd Year YELLOW

Stop if

Watch out

Check

Steps

Say this to your foreman

Before I fasten this duct to the cabinet, can you verify the allowed fastener location/length? I don't want to hit controls, wiring, coil, or internal parts.

More in Equipment Connections: RTU, AHU, VAV, Fans & Louvers