What's the protocol for crane lifts if the wind speed exceeds 20 mph?

Monitoring wind metrics is a primary safety standard. If sustained wind velocities or gusts exceed 20 to 25 mph , the crane operator or lift director has the absolute authority to shut down all hoisting operations immediately . Wide, flat-sided HVAC units act like giant sails in high winds, creating violent swinging forces that can tip a crane or smash the load into the side of the building.

['Monitoring wind metrics is a primary safety standard. If sustained wind velocities or gusts exceed 20 to 25 mph , the crane operator or lift director has the absolute authority to shut down all hoisting operations immediately . Wide, flat-sided HVAC units act like giant sails in high winds, creating violent swinging forces that can tip a crane or smash the load into the side of the building.']

Equipment Connections: RTU, AHU, VAV, Fans & Louvers 4th Year RED

Stop if

Steps

Say this to your foreman

what's the protocol for crane lifts if the wind speed exceeds 20 mph?

More in Equipment Connections: RTU, AHU, VAV, Fans & Louvers