What is the process for submitting an RFI (Request for Information) when a clash stops work?

Stop your installation crew safely before hanging pieces that will clash.

['Stop your installation crew safely before hanging pieces that will clash.', 'Draft a clear, precise description of the structural conflict point, referencing the exact room number, column line grid coordinates, and blueprint sheet numbers.', 'Propose a clear, smart field solution path (e.g., Request permission to transition 36x12 duct to 48x10 to clear structural plumbing main).', 'Hand this complete layout sketch packet to your foreman so they can log and submit the official RFI document to the General Contractor.']

Coordination, Clashes, Sequencing & Rework 3rd Year YELLOW

Stop if

Check

Steps

Say this to your foreman

what is the process for submitting an rfi (request for information) when a clash stops work?