What do I check for finish work: sidewall grille / register fit?
Sidewall air devices must match the wall opening, sit flat, cover the cut cleanly, and not expose a crooked duct sleeve or ugly backing.
Stop if
- The wall opening/backing is rough and the grille will not sit clean. Do you want the opening corrected before I install it?
Watch out
- Stop if the wall is finished and the grille will not cover the opening, has no backing, or conflicts with architectural elevation/details.
Check
- Dry-fit the grille before final screws.
- Check level and reveal around all sides.
- Use correct anchors/backing if wall material requires it.
- Do not over-tighten and bow the frame.
- Clean face and wall after install.
Steps
- Dry-fit the grille before final screws.
- Check level and reveal around all sides.
- Use correct anchors/backing if wall material requires it.
- Do not over-tighten and bow the frame.
- Clean face and wall after install.