Field problem

Field check

Standard work. Do it right, keep moving.

What do I check for finish work: installing lay-in diffusers cleanly?

Lay-in diffusers must sit clean in the grid, line up visually, connect without stress, and remain serviceable for TAB and maintenance.

QA/QC, Punchlist, Documentation & Turnover 1st Year GREEN

Stop if

Watch out

Check

Steps

Say this to your foreman

This diffuser sits crooked because the connection above is pulling it. Should I adjust the connection, hanger support, or wait for layout correction?