Foreman script
Verify first
Verify before you commit. Cheap to catch now.
The riser is now off at the fourth floor even though each joint looked close. I rechecked from the floor benchmark and found the error has accumulated. Where do you want the correction made?
vertical duct is accumulating elevation error floor by floor vertical riser cumulative elevation error floor by floor duct stop chaining each new section from the last joint. re-establish the riser from the project benchmark, floor elevations, and intended connection points, then determine where the accumulated error began. the riser is now off at the fourth floor even though each joint looked close. i rechecked from the floor benchmark and found the error has accumulated. where do you want the correction made?