Verify Roof Curb and RTU Match Before the Lift
Confirm the curb, adapter, unit model, opening arrangement, rail orientation, and supply/return locations before crane day.
Stop if
- Before crane day, can we verify this curb and adapter against the actual RTU model, opening orientation, and approved submittal?
Watch out
- Do not rely only on a shipping label or assume similar unit sizes use the same curb openings.
Check
- Match model and serial/submittal data
- Measure curb outside dimensions and openings
- Verify supply and return orientation
- Check adapter and gasket requirements
- Photograph and sign off before the lift plan is final
Steps
- Match model and serial/submittal data
- Measure curb outside dimensions and openings
- Verify supply and return orientation
- Check adapter and gasket requirements
- Photograph and sign off before the lift plan is final
Say this to your foreman
Before crane day, can we verify this curb and adapter against the actual RTU model, opening orientation, and approved submittal?