The ceiling plenum is too tight for the planned duct connection

Do not change the connection style just because the ceiling is tight. Verify finished ceiling height, connector clearance, pressure class, access needs, and get approval before switching to a low-profile joint or revised route.

Coordination, Clashes, Sequencing & Rework 2nd Year YELLOW

Watch out

Check

Steps

Say this to your foreman

The plenum at [location] is too tight for the planned connection. I measured the ceiling height and connector clearance. Do you want an approved low-profile joint, revised elevation, route shift, or detailer review before we install this run?