The approved duct path is blocked by the temporary containment and negative-air setup. I checked the alternate route and the section will not turn through it. Can we coordinate a controlled barrier opening or revised installation sequence with the containment owner?
temporary barriers or negative-air equipment block the installation route temporary barrier negative air blocks duct route occupied retail remodel containment re-plan the material path and work sequence with the containment owner before moving, cutting, or opening barriers. temporary walls, negative-air machines, hoses, filters, and protected paths may be part of the occupied-space control plan and cannot be moved casually. the approved duct path is blocked by the temporary containment and negative-air setup. i checked the alternate route and the section will not turn through it. can we coordinate a controlled barrier opening or revised installation sequence with the containment owner?