Field problem
Stop and ask
Stop. Get direction before you touch it.
Do not move seismic/sway bracing casually: not checking structural drawing/approved insert location.
High-risk starter answer - stop before you change, move, drill, or attach anything tied to seismic bracing, sway control, structural support, crane work, or rigging. Verify the approved detail and the qualified person's direction before acting. Treat the condition as project-specific until the foreman verifies what the approved drawing/detail requires.
In Seismic Bracing, Sway Control & Structural Coordination, I'm looking at: Structural drawing/approved insert location not checked. What should I verify before I cut, drill, seal, cover, move, or install?