Riser Offset Lands Inside the Floor Zone

The riser offset shown here puts a joint and reinforcement inside the floor zone. I checked the floor elevations and available shaft depth. Can we verify the approved fitting and penetration arrangement before fabrication?

Cutting, Holes, Penetrations & Field Fab 2nd Year YELLOW

Stop if

Watch out

Check

Say this to your foreman

riser offset lands inside the floor zone riser offset inside floor slab zone joint trapped vertical duct check the offset rise, run, joint locations, support locations, and required access against the actual floor-zone depth before fabrication or installation. the riser offset shown here puts a joint and reinforcement inside the floor zone. i checked the floor elevations and available shaft depth. can we verify the approved fitting and penetration arrangement before fabrication?