Riser Joint Cannot Be Completed With Shaft Wall Framing Installed

The shaft-wall framing now blocks the backside of the next riser joint. I checked access from both floors and cannot complete the hardware. Can we coordinate the approved framing and duct sequence before continuing?

Coordination, Clashes, Sequencing & Rework 2nd Year YELLOW

Stop if

Watch out

Check

Say this to your foreman

riser joint cannot be completed with shaft wall framing installed shaft wall framing blocks riser joint access duct sequence coordinate the duct-install sequence with shaft-wall framing and close-in before the framing blocks joint access, support installation, damper access, or inspection. the shaft-wall framing now blocks the backside of the next riser joint. i checked access from both floors and cannot complete the hardware. can we coordinate the approved framing and duct sequence before continuing?