Foreman script

Verify first

Verify before you commit. Cheap to catch now.

Respecting Gravity Systems

This conflict involves a gravity drain. Do we verify slope/elevation and approved reroute before changing duct?

I'm checking respecting gravity systems at [location]. I found: Duct is routed under/around a sloped drain without checking pitch and ceiling height.. This conflict involves a gravity drain. Do we verify slope/elevation and approved reroute before changing duct?

Coordination, Clashes, Sequencing & Rework 2nd Year YELLOW

Stop if

Watch out

Check

Say this to your foreman

14730 respecting gravity systems coordination, rfis & other trades yellow 2 this conflict involves a gravity drain. do we verify slope/elevation and approved reroute before changing duct? gravity drain conflict, pipe with slope in duct path, plumbing conflict, duct hitting drain duct is routed under/around a sloped drain without checking pitch and ceiling height.

More in Coordination, Clashes, Sequencing & Rework