Check plumb/level before final fastening. Temporary alignment is not final alignment.
Stop if
- Can you check this alignment before I final-tighten it?
Watch out
- Do not lock duct down while it is twisted, leaning, or forced.
Check
- Use level/laser/string as appropriate.
- Check pitch/slope requirement if any.
- Verify hanger load and alignment.
- Tighten after final position is confirmed.
- Recheck after adjacent pieces are connected.
Steps
- Use level/laser/string as appropriate.
- Check pitch/slope requirement if any.
- Verify hanger load and alignment.
- Tighten after final position is confirmed.
- Recheck after adjacent pieces are connected.