Common mistake
Stop and ask
Stop. Get direction before you touch it.
A written rigging plan for any lift over 1,000 lbs or any lift over a public area is mandatory. The plan must include equipment weight and center of gravity, crane capacity, rigging configuration, and communication protocol. Have the foreman sign it before the crane arrives.
More in Equipment Connections: RTU, AHU, VAV, Fans & Louvers