Not communicating field conflict before fabricating fix
Do not fabricate a field fix before telling the foreman what the conflict is. A fix without approval can become your rework.
Stop if
- Here is the conflict: . Do you want a field fix, RFI, or revised piece before I fabricate anything?
Watch out
- Do not build your own fix and hope it matches what the foreman wanted.
Check
- Describe the conflict in one sentence.
- Take a photo with location/grid/system.
- Check latest drawing/detail.
- Ask before cutting/fabricating/offsetting.
- Write down the direction if the fix changes the route.
Steps
- Describe the conflict in one sentence.
- Take a photo with location/grid/system.
- Check latest drawing/detail.
- Ask before cutting/fabricating/offsetting.
- Write down the direction if the fix changes the route.
Say this to your foreman
Here is the conflict: . Do you want a field fix, RFI, or revised piece before I fabricate anything?