Field problem

Coordinate

Tell someone or document it before you close it up.

Not asking before modifying equipment connection detail

Equipment connection details are submittal-controlled. If the approved detail does not fit the field condition, document it and get direction before modifying anything.

Equipment Connections: RTU, AHU, VAV, Fans & Louvers 3rd Year BLUE

Stop if

Watch out

Check

Steps

Say this to your foreman

The equipment connection detail at [unit tag/location] [does not fit the field condition / conflicts with another trade / appears to need modification] because [describe]. I have not changed anything yet. Do you want an RFI, or is there an approved field fix?

More in Equipment Connections: RTU, AHU, VAV, Fans & Louvers