Field problem

Stop and ask

Stop. Get direction before you touch it.

Missing sway control on long run

Do not move seismic/sway bracing casually: missing sway control on long run.

High-risk starter answer - stop before you change, move, drill, or attach anything tied to seismic bracing, sway control, structural support, crane work, or rigging. Verify the approved detail and the qualified person's direction before acting. If a run or equipment connection appears to be missing restraint, flag it instead of adding a random brace.

Seismic Bracing & Structural Coordination 4th Year RED

Watch out

Check

Steps

Say this to your foreman

This duct run is approximately [length] with no visible sway bracing. The detail shows bracing at [interval/location] but I do not see it installed. Do you want me to flag this span for brace installation before we continue?