Missing coordination around structural steel
When duct conflicts with structural steel, stop. Structure is not something an apprentice trims, drills, notches, or works around without direction.
Watch out
- Do not cut, drill, notch, grind, or modify structural steel or supports.
Check
- Photo steel and duct route together.
- Check section/detail/coordination drawing.
- Verify if route can shift without creating other problems.
- Tell foreman before cutting/drilling/field fitting.
- Ask if engineering/coordination/RFI is needed.
Steps
- Photo steel and duct route together.
- Check section/detail/coordination drawing.
- Verify if route can shift without creating other problems.
- Tell foreman before cutting/drilling/field fitting.
- Ask if engineering/coordination/RFI is needed.
Say this to your foreman
Structural steel blocks this duct route. Do you want this escalated for coordination/RFI?