Mechanical drawing and shop drawing show different duct size
Hold the install until the controlling document is confirmed. Approved shop drawings, RFIs, sketches, or addenda may control, but the field should not decide alone.
Stop if The mechanical drawing shows [size], but the shop drawing shows [size] for the same run. Which one controls?
Watch out Do not choose the drawing that matches the material just because the material is already staged.
Check Compare revision dates and approval/status stamps. Check piece marks and system/area tag. Photo both callouts side by side. Ask foreman/PM which document controls. Do not install more of that run until direction is clear.
Steps Compare revision dates and approval/status stamps. Check piece marks and system/area tag. Photo both callouts side by side. Ask foreman/PM which document controls. Do not install more of that run until direction is clear.
Say this to your foreman The mechanical drawing shows [size], but the shop drawing shows [size] for the same run. Which one controls?
Copy this