Apprentice question
Verify first
Verify before you commit. Cheap to catch now.
Line up the slip flanges or raw edges carefully. Drive sheet metal screws (tek screws) through the mating flanges spaced every 4 to 6 inches, and use high-temperature foil tape or silicone sealant to seal the perimeter completely. Take care not to puncture the internal hydronic circuit or electric element racks with long screws.
['Line up the slip flanges or raw edges carefully. Drive sheet metal screws (tek screws) through the mating flanges spaced every 4 to 6 inches, and use high-temperature foil tape or silicone sealant to seal the perimeter completely. Take care not to puncture the internal hydronic circuit or electric element racks with long screws.', '--']
how do i properly secure the reheat coil to the vav discharge?
More in Equipment Connections: RTU, AHU, VAV, Fans & Louvers