Apprentice question
Stop and ask
Stop. Get direction before you touch it.
Coordinate with the temperature controls technician to command all digital VAV box actuator motors to drive into their 100% full open position overrides via their central software control board. If the controls aren't powered on yet, you must manually decouple the actuator shaft set-screws and rotate the damper blades by hand to full open before starting the primary fans.
["Coordinate with the temperature controls technician to command all digital VAV box actuator motors to drive into their 100% full open position overrides via their central software control board. If the controls aren't powered on yet, you must manually decouple the actuator shaft set-screws and rotate the damper blades by hand to full open before starting the primary fans."]
how do i ensure all vav damper blades are in the open position before system blow-down?