Ask before moving anchors, changing spacing, deleting supports, drilling structure, or altering trapeze/seismic layout.
Watch out
Do not guess hanger spacing when the run or duct size changes.
Check
Check support locations
Check heavy fittings/transitions
Confirm approved hanger detail
Steps
Identify the support type and duct being carried.
Check approved detail or foreman direction.
Verify anchor/hardware and attachment point.
Focus on the actual issue: not checking hanger spacing after duct size changes.
Photograph or mark the condition if someone else needs to approve it.
Say this to your foreman
In Hanger Systems, Rods, Straps, Trapeze & Anchors, I'm looking at: Hanger spacing after duct size changes not checked. What should I verify before I cut, drill, seal, cover, move, or install?