Electrical Conduit Conflict with Duct
Electrical conduit often conflicts with duct routing. Need to know when to reroute vs request coordination.
Watch out
- Don't reroute without checking drawings. Don't assume electrical always wrong. Don't create field mod affecting other trades without coordination.
Check
- Which trade installed first?
- Conduit shown in this location?
- Coordination drawing or BIM?
- Priority in this zone?
Steps
- Which trade installed first?
- Conduit shown in this location?
- Coordination drawing or BIM?
- Priority in this zone?
Say this to your foreman
Electrical conduit in duct path at [location]. Reroute duct or is conduit wrong per coordination drawing?