Equipment needs real service and coil pull access. If a duct blocks the removal lane, hold the run and coordinate a layout shift before it becomes future demolition.
The duct layout at [AHU/tag] blocks the coil/access removal lane. I checked the submittal/service side. Do you want the run lowered, offset, or held for coordination?
Watch out
Do not build a permanent duct main where future coil removal requires demolishing the duct.
Check
Open or simulate opening the access door before final duct location is locked in.
Check coil pull direction and service clearance on submittals.
Measure actual clearance from duct to cabinet/service side.
Coordinate with foreman/detailer/GC if the duct line blocks removal.
Document the fix before insulation/ceiling close.
Steps
Open or simulate opening the access door before final duct location is locked in.
Check coil pull direction and service clearance on submittals.
Measure actual clearance from duct to cabinet/service side.
Coordinate with foreman/detailer/GC if the duct line blocks removal.
Document the fix before insulation/ceiling close.
Say this to your foreman
The duct layout at [AHU/tag] blocks the coil/access removal lane. I checked the submittal/service side. Do you want the run lowered, offset, or held for coordination?