Foreman script

Verify first

Verify before you commit. Cheap to catch now.

Do Not Paint Over Inspection Items

Is this item released for paint/wrap/cover, or does it need inspection first?

I'm checking do not paint over inspection items at [location]. I found: Work gets covered before the inspector/foreman verifies the detail.. Is this item released for paint/wrap/cover, or does it need inspection first?

Print Reading, Tags & Layout 1st Year YELLOW

Stop if

Watch out

Check

Say this to your foreman

14648 do not paint over inspection items qa/qc, punchlist & inspection readiness yellow 1st is this item released for paint/wrap/cover, or does it need inspection first? paint over weld, cover before inspection, inspection hold point, do not cover work gets covered before the inspector/foreman verifies the detail.

More in Print Reading, Tags & Layout