Airflow Measuring Stations
Airflow measuring stations need straight duct, access, controls wiring, and correct orientation.
Stop if
- This airflow station is near a fitting. Do we have enough straight duct and access per manufacturer?
Watch out
- Do not flip, bury, or install immediately after turbulence without checking manufacturer straight-run rules.
Check
- Confirm airflow arrow, straight run, access, control wiring side, and manufacturer requirements.
Steps
- Identify whether this is normal ductwork or a controlled/special condition.
- Confirm airflow arrow, straight run, access, control wiring side, and manufacturer requirements.
- Get the current drawing/detail/spec/submittal before changing routing, material, access, or support.
- Bring photos, location, and what you checked to the foreman before closing or covering the work.
Say this to your foreman
This airflow station is near a fitting. Do we have enough straight duct and access per manufacturer?