Line up the slip flanges or raw edges carefully. Drive sheet metal screws (tek screws) through the mating flanges spaced every 4 to 6 inches, and use high-temperature foil tape or silicone sealant to seal the perimeter completely. Take care not to puncture the internal hydronic circuit or electric element racks with long screws.

Ask a jobsite questionBack to Foreman Skills & Jobsite Productivity

Plain-English answer

Line up the slip flanges or raw edges carefully. Drive sheet metal screws (tek screws) through the mating flanges spaced every 4 to 6 inches, and use high-temperature foil tape or silicone sealant to seal the perimeter completely. Take care not to puncture the internal hydronic circuit or electric element racks with long screws.

--

Field checklist

Ask Foreman

Hey boss, I’m checking vavs & fan coils: How do I properly secure the reheat coil to the VAV discharge? I found the likely issue and want to verify the next step before I lock it in. Do you want me to adjust it now or check the drawing/detail first?

Verify before acting

Use this as training guidance. The foreman, approved drawings, project specs, manufacturer installation instructions, employer safety policy, and AHJ/code requirements always control the final answer.

Related questions in this category