A crane lift is scheduled for tomorrow, but a storm is rolling in. What is the contingency plan to secure the site?
4th YearAdvanced Problem SolvingRED · Stop / Verify
Call an immediate coordination meeting with the crane vendor and the GC superintendent to review the local marine weather radar predictions. * If high winds or heavy downpours are guaranteed, officially postpone the heavy lift to the designated backup weather day block to avoid costly standby fees. * Secure all materials currently staged out in the open on the ground level: wrap all exposed duct insulation cores in heavy plastic sheeting, strap down open material boxes to heavy pallets, and veri