How do I read the equipment schedule to know which VAV goes in which room?
2nd YearBlueprint ReadingYELLOW · Check First
Locate the specific equipment tag number (e.g., VAV-1-04) marked on the floor plan. Go to the Equipment Schedule Sheets (usually found at the start or end of the 'M' blueprints pack). * Find that matching tag row to read its required CFM airflow rating, inlet size, electrical voltage supply needs, and minimum control clearance requirements.