Printable playbook

Pre-TAB Walk Checklist

Use this before TAB/balance starts so obvious install problems do not turn into startup drama.

Field checklistMobile-firstCopy-ready ask

Use when

TAB is scheduled soon, systems are being started, or a foreman asks for a final airflow/access readiness walk.

First move

Walk by system and room. Make a punch list before TAB finds it for you.

Walk it in this order

  1. Confirm every diffuser, grille, register, VAV, damper, coil, and access panel is installed, tagged, and reachable.
  2. Check flex for kinks, sag, excess length, crushed liner, and bad support.
  3. Check branch takeoffs, taps, transitions, and fittings for obvious restrictions or wrong orientation.
  4. Check damper handles and test/balance access are not hidden by ceiling, insulation, or walls.
  5. Check visible joints, collars, boots, access doors, and openings for leakage or missing seal.
  6. Record not-ready items by room/grid/system with a wide photo and close-up.

Do not

Photos / notes to collect

Ask it clean

TAB starts [date]. Do you want me to run this pre-TAB walk and send a room-by-room punch list before they arrive?

Find matching foreman scriptsSearch Field Rescue

Rule: TinnerFlow helps you check and ask cleaner. It does not approve work. Drawings, specs, manufacturer instructions, code/AHJ, employer policy, site safety rules, and foreman direction always win.